More on Cargolux: weights and fuel burn
Note: Jon Ostrower at Flight Global has this update.
The underlying cause for the Cargolux rejection (the airline’s word) of the delivery of the first two Boeing 747-8Fs is performance.
Performance is based, generally, on two things: weight of the airplane and specific fuel consumption (SFC). If the airplane is too heavy, it may not meet the payload and/or range guarantees. If SFC is below specifications, range/payload may be affected. If you combine the two issues, a larger problem exists.
It’s been well known for more than a year that the 747-8 was “heavy” and the GEnx engines burned too much fuel. Despite the two year delay, GE hasn’t developed a performance improvement package (PIP) for the 747-8 that will be ready before the end of 2013, according to sources familiar with the situation. GE’s priority has been the 787 program.
We asked Boeing about the weight and SFC issues. Here is its response:
What’s behind the Cargolux rejection of the 747-8F delivery
Here’s an expanded version of a story we did for Commercial Aviation Online/Air Transport Intelligence:
The embarrassing last minute refusal by Cargolux air cargo to accept delivery of the first Boeing 747-8F that was planned in elaborate ceremonies 19 September is due to more than it appears on the surface, say several sources at the ISTAT European conference that got underway Sunday night (18 September) in Barcelona.
No source would be identified due to the sensitive nature of the situation and the underlying issues triggering the refusal—an overweight airplane and one that doesn’t meet promised fuel burn specifications—are real and potentially affecting future customer deliveries. But sources are universal in concluding that a new element in the Cargolux situation emerged last week to trigger the refusal.